Autumn Drive Water & Sewer Improvement — Design Meeting (Project 102785-2)

17:574 спикера
17:49
длительность
11
главы
4
спикеры
8
Идеи
water main replacementsanitary sewertemporary water serviceconstruction impactsProject 102785-2

Спикеры

4
Спикер A21%14 реплик
Спикер B71%12 реплик
Спикер C4%7 реплик
Спикер D3%7 реплик

Основные идеи

8
  • Project replaces sanitary sewer mains and water mains in the Autumn Drive / Autumn Court area (Project 102785-2).
  • City replaces city-owned service line to the property line and the meter; private plumbing (meter to building) is homeowner responsibility.
  • Temporary above-ground water lines will be used during construction; brief 15–30 minute outages occur during service transfers.
  • Sewer service will not be interrupted; new cleanouts installed at property line but building-side plumbing remains owner responsibility.
  • Contractor is responsible for damage caused during construction; contractor documents pre-construction property condition and will restore damaged features.

Важные моменты

7
  • Project area bounded by Autumn Court (N), Bel Air Circle (E), Winslow Drive & Overton Park (S), Overton Park Drive East (W).
  • City will replace water meter and meter box and repair impacted areas up to the property line.
  • Temporary water line billing: summer usage billed on prior month average; Fort Worth will credit usage above normal daily use due to temporary lines.
  • Flushing and bacteriological sampling required: two consecutive passing samples needed before connecting customers to new main.
  • Contractor will relocate trash/recycling carts if street closures block regular pickup.

Решения

4
  • City will replace city-owned water service lines to the property line, and replace water meters and meter boxes; private plumbing remains homeowner responsibility.
  • Sanitary sewer service will not be interrupted during construction; new sewer cleanouts will be installed at property lines.
  • Contractor is responsible for repairing any property damage caused by construction and will document pre-construction conditions.
  • Temporary above-ground water lines will be used during construction; water will be shut off for 15–30 minutes during service transfers and continuous flushing/sampling is required before connection.

Задачи

3
  • Update project page and send link to Overton Park Neighborhood Association board membersDina Johnson · tomorrow
  • Post YouTube video of the WebEx meeting and upload PowerPoint summary and FAQs to the project pageCity project team
  • Provide written summary/FAQs in English and Spanish (Spanish delayed until translator available)City project team

Термины

6
CCTV inspection — Using a camera inserted into sewer pipes to assess pipe condition and identify defects.
Easement — Legal right to use another's land for utility infrastructure; some sewer lines are in easements west of Autumn Drive.
Sewer cleanout — Access point at the property line providing crews a place to clear blockages; owner maintains the line from cleanout to house.
Temporary water line — Above-ground pipeline used during construction to maintain service while mains are replaced.
Bacteriological test (flushing the line) — Water sampling protocol requiring two consecutive passing microbiological tests before connecting customers to the new main.

Основное содержание

11 глав · 17:49
0:00

1. Introduction and Meeting Logistics

Спикер A0:00

Good evening, everybody, and thank you for joining us for the design meeting for the Autumn Drive Water and Sewer Improvement Project.

We are recording this, so please make sure that you are muted until the presentation is over. If you have questions during the presentation, you can go down to the right-hand corner of the screen where it says chat, and you can post your questions in the chat, and we will field those questions first.

After the presentation, then we'll open the floor to any call-in users who have questions. And I'm going to hand this over to Dina Johnson, who is your project manager. Dina?

0:39

2. Agenda and Project Team

Спикер B0:39

Good evening. Thank you for attending this design meeting. We have an agenda we're going to follow tonight. We start with introduction, project overview, project area, and frequently asked questions.

Your design project team includes myself. I'm Dina Johnson. My phone number is 817-392-7866. My email address is dina.johnson@fortworthtexas.gov. The engineering design consultant is RLG. Brent Lewis is the project manager.

1:13

3. Project Overview and Project Area

Спикер B1:13

Project overview: Sanitary sewer mains will be replaced in an area bound by Autumn Court to the north, Bel Air Circle to the east, Winslow Drive and Overton Park to the south, and Overton Park Drive East to the west. These improvements are in Council District 3. Construction will impact the Overton Park Neighborhood Association area.

Project area: We have water and sewer improvement in Autumn Drive from South Cul-de-sac, Ranch View Road. We have water and sewer in Autumn Drive from Ranch View Road to Autumn Court, and water and sewer improvement in Autumn Court from Autumn Drive to the south dead end. Also, we have sewer in an easement west of Autumn Drive from 700 feet north of the Ranch View Road at Autumn Drive intersection, 270 feet westerly, then 50 feet northerly. We have another sewer in an easement west of Autumn Drive from 1,000 feet north and 180 feet north of the Ranch View at Autumn Drive intersection to 250 north.

2:31

4. FAQs: Project Purpose, Service Lines, and Access

Спикер B2:31

We have the questions that we're going to post that most people would ask.

Why are you doing this project? Fort Worth prioritized water and sewer line replacements based on available data, which includes the water main break history, leak history, CCTV inspection, which is when we put a camera into the pipe to tell us the condition of the pipe, age of the line, line material, and whether there are lead service lines. In this instance, the project was created because of the water cast iron pipe initiative the City of Fort Worth is implementing to reduce the amount of water main breaks, as well as the condition and age of the sanitary sewer lines in the area.

Do you replace the water service line up to my house? We replace the city-owned service line to the property line. We also replace the water meter and meter box, and we will repair impacted areas on your property. We do not replace the water line from the water meter to your home or business. The service line from the water meter to your home or business is considered private plumbing, and in the event of a leak, repairs need to be done by a licensed plumber at the homeowner's expense.

Will you need access to our property? This construction is in the public right-of-way and/or in utility easements. If Fort Worth Water needs access to your property, we will contact you prior to the start of construction.

Will our sewer service be disrupted? Sanitary sewer service will not be interrupted. New sewer cleanouts will be installed at the property line. The sewer cleanout provides the crew easy access if a backup or blockage occurs. The sewer line from the cleanout to the house is the owner's responsibility to maintain.

Will our water be turned off? Water will be turned off for 15 to 30 minutes when service is transferred from the existing line to a temporary water line, and when the service is transferred from the temporary to the new line. These switchovers are done during the day. The contractor will knock on the door and let customers know when the water will be turned off. The transfer typically takes 30 minutes per house or business.

How does the temporary line impact my home and water bill? The temporary water line ensures that you are not without water during construction. In the summer months, the continuous flow keeps the water from becoming stagnant in the above-ground line. The bill for your water usage while you are on the temporary line during the warmer months is based on an average of the previous month's usage. During the winter months, water must be continually flowing through the temporary line to keep the line from freezing. Customers should also keep their faucets dripping. If you are on a temporary water line, you are advised to keep your water running when the temperature drops below freezing. Fort Worth will credit your account for water use above your normal daily use. If you see water running down the street, don't turn it off.

Before we can connect your services to the new water line, the inspector has to take water samples. We call that flushing the line. The water flow from flushing the line will be continuous until two consecutive water samples pass the bacteriological test. You will be connected to the new water main after we achieve those two successful samples. When it is time to sample the water flowing through the new water main, the contractor will place traffic cones around the valve to prevent anyone from parking over the valve. Don't move the cones, don't park over the cones, and don't turn off the water valve.

7:00

5. FAQs: Property Impacts, Irrigation, Watering Rules, and Traffic

Спикер B7:00

Are we getting a new curb, gutter, and sidewalks? Existing curb, gutter, sidewalks, and driveways will not be replaced except in certain circumstances, which includes those that are damaged by the contractor during construction. The contractor may need to remove and replace some curb and gutter and sidewalks to restore services. The contractor will also remove and replace driveway approaches and currently have water meters located in the approach that must be relocated.

What happens if my property is damaged? The contractor will take pictures and video of the property before breaking ground. We also encourage property owners to take pictures and video of their property before construction commences. Damage resulting from the contractor's activity during construction is the responsibility of the contractor.

Will the water and sewer construction affect my irrigation? If you have an irrigation system, sprinkler system, the contractor has to cap the irrigation lines before construction starts. The contractor will ask property owners to turn on their irrigation system so the sprinkler heads can be located and flagged. The contractor will replace irrigation systems that are damaged during construction.

Are there restrictions on when we can water our lawns? Yes, requirements include no watering by irrigation systems or sprinklers between 10:00 AM to 6:00 PM. Watering by handheld hose, drip irrigation, or soaker hose is allowed at any time. Twice a week, irrigation system or sprinkler schedule will assign days for all water customers. We have Monday, no watering allowed. On Tuesday and Friday, non-residential sites such as apartments, businesses, parks, and common areas. On Wednesday and Saturday, we have residential addresses ending in even numbers. On Thursday and Sunday, we have residential addresses ending in odd numbers.

Will there be lane closure during construction? Expect lane closure during construction when the contractor is installing the water and sewer lines. Signs will be posted to alert motorists. The hours of construction are 7 AM to 6 PM Monday through Friday, and if requested by the contractors, sometimes he will work from 9 AM to 4 or 5 PM on Saturdays.

Will the city's trash truck be able to pick up my trash and recycling during construction? If your side of the street is closed on your scheduled trash collection day, the contractor will take your trash and recycling carts to the opposite side of the street so the trash collection vehicle can pick it up.

10:17

6. Timeline, Resources, Contacts, and Reporting

Спикер B10:17

Timeline. This is a design meeting. The next steps include advertising the project for bids, opening bids, City Council approval to award the bid to the contractor, pre-construction meeting with the contractor and inspector, a community construction meeting to update those impacted by the project, and construction starts.

Where can I get more information? Progress will be updated on the City of Fort Worth website at the link below. You can also go to www.fortworthtexas.gov and put the project number 102785-2 in the search bar on the homepage. The link to this meeting video, the project map, and the project summary frequently asked questions will be linked to this project.

Contacts: Myself, I'm Dina Johnson. My number: 817-392-7866. My email: dina.johnson@fortworthtexas.gov.

How do I report an emergency or non-emergency? For emergencies, water main breaks, or sewer backups, 24 hours a day, you can call 817-392-4477, select option 1. For non-emergency water call center, you can, from 7:00 AM to 7:00 PM, Monday through Friday, you can call 817-392-4477, plus city holidays. Download the MyFW app from the App Store or Google Play. You can report sewer overflows, leaks, and water main breaks, missing or broken meter lids, water theft, water violations, no water service, water pressure issues, and other sewer concerns.

12:17

7. Opening Remarks and Start of Q&A

Спикер B12:17

With that, I want to thank you for joining us this evening. And now we can take questions.

Спикер A12:24

Okay, we don't have any questions in the chat. If you have some questions, or you want to see a slide that you may have missed, go ahead and unmute yourself and ask.

Okay, we've got Brad, Ginger, Jack, and Robert.

Спикер C12:57

Do I go first? And if I'm Brad,

Спикер A13:02

You can go first. Yes, sir.

13:04

8. Discussion of Utility Coordination (Gas and Sewer Work)

Спикер C13:04

Yes, on the diagram, there's also going to be gas work being performed on Autumn and Autumn Court on the north side. It was—I'm sorry, did you make a statement?

Спикер B13:18

Yeah, we don't normally—we're just replacing water sewer. This is for other utilities.

Спикер C13:24

No, that's not my point. My point is there will be gas work going on because they've already said they're going to be doing gas work.

And that actually was my question. Were you aware that there was going to be gas work being done at the same time you're planning to do the sewer work?

And I guess the answer is no.

Спикер B13:42

No, the answer is no, because normally we send the plans for utility clearance, and we like them to be out of the project when we start construction.

Спикер C13:50

So, are you aware that they are planning to do gas work on Autumn and Autumn Court right now?

Спикер B13:55

Uh, yeah.

Спикер C13:58

Okay, well, they do—

Спикер B13:59

Because construction is going to start next year, normally they start way ahead of us to do the replacement, whatever they need to repair on the gas lines.

Спикер C14:08

Okay, so they'll do all that work before you get started. Thank you.

Спикер B14:12

Yes.

Спикер C14:15

Thank you.

Спикер B14:16

You're welcome.

Спикер A14:18

Okay, and I should say that Jack has joined us from Councilmember Crane's office, so he is on the call with us if you have any questions.

Okay, so we've got Brad, Ginger, Robert. Do you have some questions, or do you want to see a slide?

Спикер B14:37

I can't hear— I can't hear Brad.

14:42

9. Project Materials, Links, and Contact/Email Procedures

Спикер D14:42

Are we going to get an email confirming a lot of this, all these slides, or—

Спикер A14:48

I can send it to the Overton Park Neighborhood Association, but Dina, can you go to that page link? I think it's— This one? Yeah, there you go.

Yes, everything will be linked to that page. We will create a YouTube video out of this WebEx meeting, and we will also have written summary FAQs that are a copy of the WebEx PowerPoint. But if you don't want to go watch the video, you can read it. And generally, we have that in English and Spanish. My translator is out with surgery, so the Spanish translation probably will not be posted until the 1st of April.

Спикер D15:34

So, are you going to send us this link?

Спикер A15:39

Once the project— I should be able to get the project page updated tomorrow, so I can send that to the board members of the Overton Park Neighborhood Association. Are you on the board?

Спикер D15:52

No, I just, I just want to know how I get this link.

Спикер A15:59

Okay. Do you want to put your email in the chat? Can you do that?

Спикер D16:03

I can, if I know—figure out how to do the chat.

Спикер A16:06

Okay. Just click on chat in the bottom right-hand corner.

Спикер D16:09

Okay. I got it.

Спикер A16:11

Okay.

Спикер D16:12

Very good. I'll do that.

Спикер A16:14

And if you all signed in with an email, we do get an Excel that shows the email addresses. And if you did that, then I'll be able to send the information to you.

Спикер D16:26

Okay, that'll work. Thank you.

16:36

10. Questions and Construction Schedule

Спикер A16:36

Okay, does anyone else have questions? We're in the design state, and, you know, what did we say about when we would come back with a construction public meeting?

Спикер B16:50

Sally, could you say that again? I'm sorry.

Спикер A16:54

When do you, when do you expect construction to start? I'm sorry, I missed that part. Well,

Спикер B17:00

We're going to advertise in the winter of this year, so probably we can start by the spring of next year construction.

17:12

11. Next Steps and Closing Remarks

Спикер A17:12

Okay. So, we'll come back to you guys in the spring of '23, and we'll have a lot more answers because Dina will have a chance to talk to the contractor and find out where he's going to start, um, north end, south end, however that's going to go. Yes. Dina, do you have anything else?

Спикер B17:41

No. I want to thank everybody for joining us this evening.

Спикер A17:47

Thank you, everybody.

Спикер B17:49

Thank you.